Eldeco Echoes of Eden is in early-stage ground works: foundation/excavation is in progress across the 5-acre plot in Sector 22D, Yamuna Expressway, Greater Noida. The project (UP RERA UPRERAPRJ125342/02/2026) was RERA-registered in February 2026. All 3 towers — Haven, Elysian, Caelum — share the same phased construction schedule. Possession date per RERA filing: January 2031. This tracker is updated on the 1st of each month; the last update was .
At-a-Glance Status
Progress percentage is a conservative indicative figure based on visible ground activity and stage milestones. It is not an official developer or RERA metric. Verify milestone certificates on the UP RERA portal.
Construction Milestone Timeline
All milestone dates below are planned targets based on the January 2031 possession commitment under RERA. Actual milestone completion depends on construction progress and will be updated here monthly. The done and in progress states are clearly date-stamped so you can track velocity over time.
RERA Registration Done
Project registered with UP RERA under UPRERAPRJ125342/02/2026. Land acquired by Eldeco Sohna Projects Ltd. Layout approval, building plans and YEIDA clearances filed. All buyer-facing disclosures uploaded to the UP RERA portal.
Completed: February 2026Site Mobilisation & Boundary Fencing Done
Site office established, contractor mobilised, boundary fencing and hoarding erected. Water and power connections commissioned for construction use. Soil investigation (geotechnical report) completed — required before raft design is finalised.
Completed: March–April 2026Excavation & Foundation Pit In Progress
Bulk earthworks excavation underway for all 3 tower footprints (Haven, Elysian, Caelum). Dewatering and shoring being carried out. This stage runs parallel across towers. Foundation pit dimensions being maintained as per structural drawings.
In progress — as of June 2026Raft Foundation / Podium Works Planned
Raft foundation pours for all 3 towers. Podium-level works including basement (if applicable), plinth, and ground-floor slab. This is the RERA "foundation milestone" that triggers the first construction-linked payment under the 30:40:30 plan.
Target: Q4 2026 – Q1 2027 (indicative)Tower Slab Construction — Haven, Elysian, Caelum Planned
Reinforced-concrete slab-by-slab construction up all 3 towers to G+30. This is the longest phase (~24–30 months), progressing floor by floor. RERA milestone certificates are issued at the structure milestone, triggering the second construction-linked payment tranche.
Target: 2027 – 2029 (indicative)Structure Top-Out (Terrace Slab) Planned
Final (G+30) floor slab cast on all 3 towers. External facade and waterproofing begin simultaneously. Terrace top-out is a visible milestone and is celebrated on-site — photos will be posted here.
Target: 2029 – early 2030 (indicative)Finishing Works Planned
Internal plastering, tiling, flooring (vitrified), electrical and plumbing fit-outs, VRV centralised AC system installation (every unit), kitchen carcass, wardrobe carcass, lifts (5 per tower), common-area finishes, landscaping, 75,000 sq.ft clubhouse works. RERA finishes milestone triggers the third construction-linked tranche.
Target: 2030 (indicative)OC & Possession Handover Planned
Occupancy Certificate (OC) obtained from YEIDA. RERA-mandated possession notice issued to buyers. Final 30% payment collected. Physical handover with unit inspection, key handover, society formation (RWA). Stamp duty and registration on the sale deed.
RERA Possession: January 2031All "planned" milestones show indicative targets. Actual dates depend on construction velocity and will be updated here as they occur. RERA allows the developer to apply for an extension per prescribed norms. Verify the latest milestone certificates on the UP RERA portal.
Per-Tower Status
The project has 3 towers — Haven, Elysian, and Caelum — each G+30 (ground + 30 upper floors). All three are in the same early-stage ground works phase as of June 2026.
Tower Haven
HavenExcavation in progress. Foundation pit being prepared. G+30, approx. 186 units. All configurations (2 BHK to 4 BHK penthouse) available in this tower.
As of June 2026Tower Elysian
ElysianExcavation in progress. Foundation pit being prepared. G+30, approx. 186 units. Central tower in the 5-acre master plan layout.
As of June 2026Tower Caelum
CaelumExcavation in progress. Foundation pit being prepared. G+30, approx. 186 units. Adjacent to the 3-acre central greens.
As of June 2026Monthly Site Photo Log
Photos are taken on authorised site visits by Vidastu Advisory. They represent the state of the site on the visit date and are not a representation by the developer. Earlier months will appear below as the archive grows.
Monthly Detailed Construction Write-ups
Each month, a detailed construction and market update is published with additional context on corridor developments, pricing status, and what to expect in the following month. This tracker page gives the visual/photo summary; the blog posts carry the full narrative.
Monthly updates are posted on or around the 1st of each month. Subscribe via WhatsApp to receive updates automatically.
Possession Date — What RERA Says
| Item | Detail |
|---|---|
| RERA Project ID | UPRERAPRJ125342/02/2026 |
| RERA Possession Date | January 2031 |
| Developer | Eldeco Sohna Projects Ltd (Eldeco Group) |
| Track Record | Est. 1985 · 200+ projects · 30,000+ families |
| Structure | 3 towers, G+30 each, 558 units, 5 acres |
| Channel Partner | Vidastu Advisory, UPRERAAGT000309/01/2026 |
January 2031 is the date filed with UP RERA. Under RERA, the developer can apply for an extension with documented justification — it is NOT automatic. Buyers who book under the RERA-registered AFS have recourse under RERA Section 18 (refund + interest) if possession is delayed beyond the RERA-committed date without extension approval. Always cross-check the latest possession date on the UP RERA portal before booking.
Stay Updated or Book a Site Visit
Sachin Bansal will add you to the monthly construction update list and can arrange an authorised site visit — so you can see the progress in person before deciding.
Get Monthly Updates + Cost Sheet
Sachin Bansal (VP Sales) · Vidastu Advisory
No brokerage charged to buyers. By submitting you agree to be contacted on the number provided. We never share your details.
RERA Disclosure & Data Accuracy Notice
This construction tracker is maintained by Vidastu Advisory (UP RERA Channel Partner UPRERAAGT000309/01/2026), an authorised channel partner of the project registered under UPRERAPRJ125342/02/2026. Vidastu is not the developer or seller.
Milestone statuses, progress percentage and photo content reflect field observations at the time of site visits, not official developer or RERA communications. Always verify the latest RERA-filed milestone certificates, approved plans and possession date on the UP RERA portal before any payment commitment. Construction timelines are indicative and subject to revision.