The Real Estate (Regulation and Development) Act 2016 provides Eldeco EOE buyers with two distinct warranty periods after possession: (1) 5-year structural warranty under RERA Section 14(3) covering load-bearing structural defects, water-proofing failures, and major service-system failures (electrical, plumbing); (2) 1-year fit-and-finish defect liability covering flooring, fittings, painting, joinery, doors, windows, kitchen / bathroom finishes. During handover, the buyer signs a snag-list documenting any pre-handover defects — these MUST be rectified at developer cost. For defects discovered post-handover within the warranty period, the developer is legally obligated to rectify; non-compliance can be escalated to the UP RERA Adjudicating Officer. RERA: UPRERAPRJ125342/02/2026. Last reviewed: .
The Two-Layer Warranty Framework
Indian residential property buyers under RERA Act 2016 have one of the strongest warranty regimes globally for new construction. Two distinct periods apply at Eldeco EOE:
Layer 1 — 5-Year Structural Warranty (RERA Section 14(3))
This is the headline warranty. For 5 years from the date of possession, the developer is legally liable for any structural or major-system defect in the unit. Covered scope:
- Load-bearing structure — columns, beams, slabs, foundation, load-bearing walls. Cracks beyond hairline thresholds, settlement, structural failure.
- Water-proofing — leakages from terraces, balconies, bathrooms, kitchen sinks, exterior facade. Including water seepage into walls.
- Major service systems — electrical distribution panels, water supply mains, drainage mains, lift mechanical systems, common-area HVAC.
- Materials and workmanship — any deficiency in material standards committed to in the AFS.
The developer's obligation under RERA is to rectify free of charge within 30 days of written notice, with no cost passed to the buyer. Non-compliance is escalatable to the UP RERA Adjudicating Officer.
Layer 2 — 1-Year Fit-and-Finish Defect Liability
For finishes and fittings, the standard industry warranty (codified in the AFS) is 1 year. Covered scope:
- Flooring — tile cracks, lifting, polish failures, grout issues
- Paintwork — peeling, blistering, mismatched colour patches
- Wooden joinery — door alignments, wardrobe shutters, kitchen cabinets, hinges
- Bathroom CP fittings — taps, showers, WC seals, faucet mixers
- Kitchen — counter, chimney, sink, plumbing fixtures
- Windows + balcony railings — sliding mechanisms, weather seals, glass alignment
- False ceiling, modular electrical — switches, sockets, ceiling-mount fixtures
- Plumbing at fittings level — leaks at faucet bases, drainage at washbasin
Normal wear-and-tear from use is NOT covered; manufacturing defects ARE. The 1-year clock starts from handover date.
The Handover Day — What Happens
Once OC is issued and the buyer's final 30% possession-stage payment is cleared, the developer schedules a handover appointment. Typical sequence:
- Pre-handover walkthrough — buyer (or representative) physically walks the apartment with the developer's handover team. Typically 60–90 minutes per unit.
- System checks — every electrical socket tested, every tap turned, every door opened/closed, every window operated. The handover team marks defects on a snag-list.
- Documentation — snag-list signed by both buyer and developer's representative. Each defect itemised with rectification commitment date.
- Key handover — keys handed to buyer subject to defect-rectification commitment. In some cases, buyer takes possession with defects pending; in major-defect cases, handover is deferred.
- Documentation kit — buyer receives: OC copy, electricity / water connection documents, lift operating instructions, common-area schedule, RWA-formation notice (if applicable), warranty documentation for fittings (taps, kitchen, VRV AC).
- Defect rectification period — typically 30–60 days for finish-level defects identified on the snag-list. Developer engineers visit, rectify, sign-off completion.
- Final acceptance — buyer signs final acceptance once rectification complete OR with documented exceptions for unresolved items.
What to Inspect During Handover — A Practical Checklist
| System | Specific checks |
|---|---|
| Walls and ceilings | Hairline cracks, paint blisters, dampness patches, plaster bumps, ceiling-mounted fixtures alignment |
| Flooring | Tile alignment, gaps in grout, hollow tiles (tap to check), polish uniformity, level (no slope where unexpected) |
| Doors and windows | Operation (smooth open/close), latch alignment, weather seals, glass for cracks, sliding mechanism on balcony doors |
| Electrical | Every socket tested with a test light, every switch operated, MCB panel labeling, earthing test (request electrician) |
| Plumbing | All taps turn on/off, drainage at every sink, WC flush operation, shower head and faucet mixer, water pressure |
| VRV AC | Each cassette operates, remote controls test, drain pipes clear, no leaks at indoor unit casings |
| Kitchen | Modular kitchen alignment (if optional package taken), chimney operation, gas point, counter for chips/cracks |
| Bathroom | CP fittings hand-tightness, exhaust operation, water-proofing at floor-wall corners (visible signs of seepage) |
| Balconies | Railing rigidity, floor slope toward drain, water-proofing membrane visible at floor-wall edge |
| Common areas | Lift operation, lobby finishes, parking demarcation, fire-safety equipment placement |
Raising Defects Post-Handover
For defects discovered after handover, within the warranty period:
- Written notice to developer — email or registered letter describing the defect with photographs. Include unit number, AFS reference, RERA registration number.
- 30-day rectification window — RERA expects rectification within 30 days; for complex structural issues, longer with documented explanation.
- Documentation — keep all written correspondence; this becomes evidence if escalation needed.
- Verification after rectification — sign off completion only after the defect is fully resolved.
The RERA Complaint Mechanism — If Rectification Fails
If the developer doesn't rectify within the warranty period or refuses outright, the RERA Act provides a formal complaint mechanism under Section 31:
- File a complaint with the UP RERA Adjudicating Officer (online via the UP RERA portal).
- Pay the prescribed fee (typically ₹1,000–₹5,000 depending on case value).
- UP RERA notifies the developer and seeks response.
- Hearings scheduled; both parties present evidence.
- Adjudicating Officer issues order — typically within 60–180 days.
Orders can include: mandatory rectification, monetary compensation, interest on delayed rectification, refund of investment, and in extreme cases, project deregistration. UP RERA's track record on residential complaints is generally buyer-protective.
Maintenance Transition — Developer to RWA
For the first 2-3 years post-handover, common-area maintenance is managed by the developer's facilities team or their appointed Facilities Management Company. After full project handover, maintenance transitions to a Resident Welfare Association (RWA) formed by residents under the UP Apartment Ownership Act.
Key elements:
- IBMS (Interest-Bearing Maintenance Security) collected at booking, transitions to RWA at handover transfer.
- Monthly maintenance — typically ₹3–5/sq.ft for projects of Eldeco EOE scale.
- RWA formation — within 2-3 years of project handover; governance per UP Apartment Ownership Act.
- Common-area defects discovered post-handover — buyer's complaint goes to developer (during defect liability period) OR RWA + developer (jointly, if RWA has assumed common-area responsibility).
What Vidastu Coordinates at Handover
Vidastu's involvement at the handover stage:
- Handover-day attendance — Sachin (or Vidastu's facilities expert) accompanies the buyer through the inspection walkthrough, identifying defects the buyer might miss.
- Snag-list template — pre-prepared checklist covering all common defect categories; ensures comprehensive inspection.
- Documentation supervision — verifying that the snag-list is properly signed and dated; that rectification commitments are documented with specific dates.
- Post-handover follow-up — weekly check-ins with the developer's facilities team until all snag-list items are rectified.
- RERA complaint coordination — if rectification fails, Vidastu prepares the Section 31 complaint documentation.
Bottom Line
The defect liability framework at Eldeco EOE is among the most buyer-protective in India — driven by RERA Section 14(3)'s 5-year structural warranty and the 1-year fit-and-finish coverage. The handover day is the most important inspection moment: defects identified then are easiest to rectify; defects missed and discovered later require post-handover complaint mechanisms. The practical advice: take your time at handover (allow 90+ minutes), bring a checklist, bring Vidastu, and document every defect on the signed snag-list. The RERA framework + Eldeco's reputation as an NSE/BSE listed developer means the developer-side cooperation rate on rectification is high; the formal RERA complaint mechanism is a useful backstop but rarely needed.
Want a Handover-Day Checklist? Sachin Walks the Snag Process
Sachin Bansal, VP Sales, Vidastu Advisory — UP RERA channel partner UPRERAAGT000309/01/2026. Zero buyer-side brokerage.
📞 Call Sachin — +91 99583 02906 💬 WhatsApp